Petrohan Reservoir – Overhaul of the reservoir and performance of PVC protecting waterproof system.
Repair campaign was implemented, which covered:
- Cleaning the reservoir from sediments bigger than 16800 m3;
- Repair of the damaged areas on the slopes and bottom of reservoir;
- Rehabilitation of the whole equipment and reinforce concrete constructions;
- Installation of waterproof synthetic geomembrane on the walls and bottom with total area 45500 m2.