Topolnitsa HPP – Erection of draining station for water take off at high wave
The project includes design, delivery, installation and commissioning of the following equipment:
- Delivery of new drain submerged pump AMAREX KRT 150-315.
- Drain pump control panel, cable routes, power and control cables.
- All types of construction and erection works for installation of the equipment and new penstocks (seamless steel pipes acc. to DIN 2448, DN200) for discharging the water out of the HPP.
- Installation of DN 200 covered back pressure valve at the pipeline end, to discharge water from the drainage gallery;
- Drilling works for construction of the route.